Emily asked for a handkerchief to have at the temple quite a while ago. I tried to make some, but my hems where huge and bulky... just not right for a dainty handkerchief! So I gave up....
Then, this Sunday I decided I should do something Sunday-like, especially since I missed church. Out came the sewing machine, muslin, and a hemming foot on my sewing machine. I'd never really tried it before. I messed around and finally got a pretty good small hem.
I could then produce this:
Isn't it way cool? I am so impressed with myself! I used a tiny crochet hook and the thinnest crochet thread I had.See that cool embroidery in the corner? I printed it off my computer and then just satin stitched over the black. Unfortunately, I learned that when you stitch over paper... It stays under ur stitches! I spent hours trying to pick the black paper out. I missed only a few small pieces but then those bled ugly purplely ink onto the muslin. I called my mother in a panic and after her many suggestions I finally just bleached it. I also went to the fabric store the next day and got some marking stuff for next time.... although I'm not so sure there will be a next time. That was hard work!
Emily asked me if I had put "ENH" as her initials but I knew "EH" was going to be hard enough so I didn't, even though I had thought about it :-) (Yes, I told her all about what I had done even though I was planning on it being a surprise cuz I was so excited for her to get it! I told her on the day I mailed it so I was silent for 2 days. )
As a side note... here is some squash I've gotten from my garden (most of u have seen this picture on Emily's blog)
I put the screw drive in there for scale (OK, so its a tiny screwdriver).While I was ill, I didn't feel well to do anything in the garden but water so on Monday I ended up with these monstrosities.
Isn't it crazy how fast those suckers grow?PS.. I've taken quite a few tomatoes off my plants as well, but they go straight from the vine to my sandwich.. no time for pictures!
With a few trips to here
but then back up to here
because watching TV was too tiring, let alone crocheting. There was also some time spent here
while talking on the phone to loving sisters checking up on me.
cuz it helped me breathe. But always back to here
I am sick of being sick. I love the fact that we have this (all of which I used)
And as much as I love lazing around here when I'm well,
Im sick of it.
So.. how was ur Memorial Day Weekend?
Here is AH talking to a Carpenter.
Remember that carpenter? I was excited to watch him go out onto the arch. It was around 2pm so one shift had ended and the next one hadn't started. It's too hot in Nevada to work through the middle of the day. I thought it was so cool seeing the guy all decked out and climbing those ladders, but I wasn't about to go out there even though Akiko suggested I could :-). Arvid didn't seem that interested either.
Do you see him there at the side, climbing?
AH told us they were pouring lengths of about 25 feet each side on a 6 day schedule. When they first started they were working at a 45 degree angle and everyone was new at it so the cycle was more like 25-30 days between pours. He said they kept dropping things and having a really hard time. He also told us that the thickness of the boxes (they are hollow) were 1'-6" at the arch and only 12" for the towers. Can you imagine? Seems very small for such a massive structure. AH told us wind was the governing factor in design which is one of the reasons its so small. You can imagine how strong the wind can get channeled down through the canyon.
On the Arizona side, we saw a couple of rebar cages set up and it looked like they were only using a #8 bars spaced around 12". I've specified #10's at 6" for a retaining wall before! Arvid asked about why they decided to do Cast-in-place rather than precast concrete. AH said that logistically it wouldn't work. I can't remember the details anymore and it makes me mad... I think I'll have to ask Arvid :-)
And I couldn't resist putting in this GQ picture of Arvid, even though most of u don't know him.
Look at those huge cranes in the back! They are used to take material out to the ends. Those are the things that fell a year ago and set everything back a year.
Essentially, right now the bridge is a suspension bridge, but when it is finished it will be an arch bridge. Those tall pylons have a pinned connection at the bridge (as opposed to a fixed connection). This way they can move around as work continues alternately on each side.
Akiko's husband said they try and keep things as even as possible and check the movement many times a day. That's why this is such a big job because they had to design the structure to withstand construction, not just the final loads as a finished product. For example, right now the concrete is experiencing tension from being suspended above the bridge but once it becomes a full arch it will all be under compression.
That's the whole point of arches. AH said you could hear the concrete cracking under the stress when you are out there, especially as it expands and contracts with the changing of the temperature throughout the day. These cracks will close once the "keystone" (or in this case, "key concrete section" :-) is in place.
Here is the view they will get from the bridge (well.. at one side anyways :-)
The plan is to get the arch done, then work on the roadway from the center out. The hard part will be attaching the columns to the arch.
I don't know what they are testing. Accidents? I bet they still happen. Speeding cars? I'm certain they still happen. I know it didn't change my behavior much :-)
Then Emily took me to a play at the Hale Center Theater in Orem. It wasn't a very big theatre and I was a little nervous at first because they were going to do Shakespeare's "As you Like It" and I haven't had good luck with little theatres in the Provo area. However, they told us it was going to be silly and then proceeded to be silly!
Shakespeare really isn't very nice to woman! The only thing I couldn't figure out was why they were wearing Edwardian/Elizabethan outfits.... and then spoke Shakespearean English. But it was pretty funny and the acting was well done. Emily and I agreed that the main guy was kinda handsome.
We also put up the chicken wire for the peas to climb.

The planting also needed to be recreated since I had had the camera the day before.
We also RIPPED up the carpet on her porch. That was pretty satisfying especially after Emily put a new blade in the exacto knife. I felt so powerful! I went through 2 blades after that cuz that carpet was TOUGH.




I'm kinda upset about it cuz I needed pink buttons but wanted a bigger size. Oh well. I guess u get what u paid for :-)
I think I did a great job.
As a final note... after the Trek it hurt quite a bit to kneel. On Saturday when I got into my biking outfit I found out why.
Look at those bruises (the camera washes them out)! Sad thing is.. I don't know how I got them!